Project Information

 

Project Title A4042 Penerlleni to Llanover Resurfacing and Goytre Bends 40 mph Zone
Route No. A4042
Grid Ref: 332080, 206200
Programme Type Skidding and Local Safety Schemes
Project stage Design
Designer Capita Symonds
Project Description

Following the analysis of the recent surfacing condition surveys there are sections of the carriageways which require improvements / reconstruction.

Under the scheme the existing 40mph speed limit at Goytre and will be extended and include a section of the A4042 towards Abergavenny. The speed reduction is intended to reduce the number of accidents at the Goytre bends.

The South Wales Trunk Road Agency’s Framework Contractor, Alun Griffiths are to undertake the construction of the scheme and works will commence in November 2007. The works are to be completed in November 2007.


Aim of Project / Benefits

The aim of the project is to extend the existing 40mph speed limit at Goytre towards Abergavenny. The speed reduction over this extended length is required to reduce the number of accidents at the Goytre bends.

The surfacing of the carriageway is to be resurfaced between Penperlleni and Llanover, to extend the life of the road and to reduce the maintenance cost of patch repairs in the future.


Start Date Duration Completion Date
October 2007 1 Month November 2007
Total Project Value (£) 270,000
Pre / During Construction Photographs Post Construction Photographs